某型直升機加裝噴灑設備的電氣負載分析

打開文本圖片集
摘 要:為保證機載系統(tǒng)的正常工作,電氣負載分析(ELA)工作是機載電子電氣設備加改裝工作中非常重要的一步,在分析相關適航條款基礎上,總結電氣負載分析過程與方法,開展某型直升機加裝噴灑設備的ELA分析,表明對適航條款的符合性,為該型直升機加裝噴灑設備的適航取證工作提供必要技術支撐。
關鍵詞:直升機;噴灑設備;ELA;適航;電纜載荷
中圖分類號:V242.2 文獻標志碼:A 文章編號:2095-2945(2025)10-0079-04
Abstract: To ensure the normal operation of the onboard system, electrical load analysis (ELA) is a very important step in the modification and upgrading of onboard electronic and electrical equipment. Based on the relevant airworthiness regulations, the process and methods of electrical load analysis are summarized. The ELA analysis for the installation of a spraying device on a certain type of helicopter is carried out, which demonstrates compliance with the relevant airworthiness regulations and provides necessary technical support for the certification of the installation of the spraying device on the helicopter.
Keywords: helicopter; spraying equipment; ELA; airworthiness; cable load
電氣負載和電源容量分析是對直升機的供電狀態(tài)進行檢查,保證直升機電源系統(tǒng)容量在預期的運行環(huán)境和條件下滿足全機負載的用電需求,使其處于安全運行的狀態(tài)。(剩余4930字)